Factory Lead Times · Commercial & Applied

Lead Time Reference

Coverage
York · Quantech · AHU
NORMAN, OK — SPLITS & ROOFTOPS
Publication 5/27/2026
Lower
+Higher
0No Change
Equipment
Status
Line Product Type Weeks Change Comments
York Notes:
  • Premier 90-150 (**) — contact ASG for current build slot availability; 20 weeks is a floor, not a commitment.
Commercial Stock List

In-Stock York Commercial Units

Coverage Splits · Heat Pumps · Packaged
Updated 6/7/2026
Segment
Series
Voltage
Refrigerant
Availability
Tons ±10%
Tech Guides
Model Number Description Segment Series Tons Voltage Available
Stock List Notes:
  • "Available" counts reflect current on-hand inventory. Negative values (e.g., −2) indicate oversold position — contact ASG immediately.
  • Refrigerant shown in model description — R-454B is current-gen A2L, R-410A is legacy HFC, SEER models are 1-stage base-tier units.
  • For Sun Core, Sun Choice, Sun Pro, Small Sunline availability on commonly-quoted configs, see the main lead time table above.
QUANTECH CHILLERS
Publication week of 5/29/2026
Cooling
Compressor
Product Type Quantech Product Current LT (wks) Comments
Quantech Notes:
  • All Quantech chiller lead times shown are current as of 5/29/2026 publication.
  • For air-cooled models, check the stock list below — a build-ready unit may be available in days, not weeks.
  • Screw chillers built on Style A and Style B platforms have different tonnage splits — verify platform fit against job tonnage.
Air Cooled Scroll Stock List

In-Stock Quantech Chillers

Updated 6/8/2026
✓ Freight to First Destination Included ✓ 12 Months Parts Warranty Included
Tons ±10%
Voltage
Refrigerant
Coil
Availability
Tons Model Number Qty In Stock Next Available V-Ph-Hz MCA Max Fuse Full Load IPLV Flow WPD Weight Dimensions
L × W × H (in)
Refrigerant
Stock List Notes:
  • Models ending in PC are Epoxy Post-Coated Dipped Microchannel Coil units — recommended for coastal or corrosive environments.
  • Units with 208-3-60 and 460-3-60 voltages share the same rated performance (EER, IPLV, flow, WPD, weight, and dimensions).
  • "Qty In Stock" of 0 indicates no current on-hand — use "Next Available" date for planning.
  • All listed units include freight to first destination and 12 months parts warranty.
  • Standard features on all units: native BACnet (MS/TP), Modbus, and N2 communications.
YORK / JCI — SEMI-CUSTOM AIR HANDLERS
Publication 4/7/2026
1

Unit Placement

2

Additive Options

Group B — greatest only counts  ·  Group C — all stack
Group B — Factory Options (longest adds to lead time)
Group C — Freight & Transit (each adds to lead time)
3

Off-Line Features

Selecting any of these forces a 16-week minimum
Estimated Lead Time
14weeks
Indoor unit

Full Reference

A

Unit Only Lead Time

Complete Release Package received 14 wk / 14 wk
Indoor · Outdoor
B

Additive Options (greatest applies)

Option Indoor Outdoor
C

Freight Consolidation / Transit (all apply)

Step Indoor Outdoor
!

Off-Assembly-Line Features

Units with any of these features cannot be built on the assembly line. Slots are limited and fill as orders are released. Availability fluctuates with demand — limited to approximately 2 units per week.
Feature Lead Time
Release Package Requirements:
  • Purchase order made out to JCI
  • Approved submittals
  • Air handling order form
  • Filter order form
  • Discount approval as needed
How the estimate works: Lead time = A (base unit) + the single greatest option from B + all options from C. "CS" means Contact Customer Service — estimate cannot be auto-calculated. Actual consolidation and transit times cannot be accurately calculated until units are completed.